Final level Ready for Steel fixing
Realignment for Releveling as recommended by Engineers
1. Base setting -Done
We are done with levelling of Pitsand where concrete will sit.
2. Inspection -Done
Inspection by Engineers was done yesterday . They are happy . They just recommended that we adjust the levels for some boxes which is being done today and tomorrow.
3. Bending of steel-done
Steel fixing into the slab will commence on Monday next week
We expect about 3 to 4 days for the job
4. Concrete Pouring
To start next week Thursday after fixing
5. Walls to start after Concrete pouring week after next week.