25 October  2019.

A call was made the previous service day for those able to come and help with some work at the Church site. It was very encouraging to see several brothers who came to help fill up the open holes with earth where the concrete pillars had been erected. Praise the Lord the Building is slowly but surely picking up momentum. Brothers worked hard and many holes were filled up. Later in the day, an Excavator was hired to make the burden lighter. Up to now, 27 pillars are completed leaving only 8 which will be completed this week. God has been good to us. He has held the rains to allow us to finish this part of the construction work. The next stage will be the floor beams and the slab. May I take this time to thank those of you who are supporting the work. May God bless you.